Timeline

Colour appointment 20/07/17
House Demolition 05/09/17
RHS retaining September 10/09/17
Pool Shell completed 01/11/17
Clarendon to site-site works 07/11/17
LHS retaining 08/11/17
House set out is booked for the 15/11
External drainage is booked for the 17/11
Slab preparation will follow and the slab pour is booked for the 23/11
Frame will be delivered after the slab pour and the frame carpenters are booked to start on the 30/11