Timeline

Colour appointment 20/07/17 House Demolition 05/09/17 RHS retaining September 10/09/17 Pool Shell completed 01/11/17 Clarendon to site-site works 07/11/17 LHS retaining 08/11/17 House set out is booked for the 15/11 External drainage is booked for the 17/11 Slab preparation will follow and the slab pour is booked for the 23/11 Frame will be delivered after the slab pour and the frame carpenters are booked to start on the 30/11